Daily energy demand reached 18.5 million kilowatt-hours, out of which 4.5 million are imported by CEZ Distribution, to cover losses in the network. The biggest demand is at 20 o’clock in the evening with 1.1 million kilowatt hours.
Currently, the largest manufacturer is HPP Koman with 5.7 million kilowatt hours, the second HPP Vau and Dejes with 2.56 million and HPP Fierza with 1.8 million kilowatt hours. Remaining part produce other hydro power plants.
Source; Serbia Energy See desk