The Bistrica hydropower project in Bosnia’s Republic of Srpska has launched a €32.3 million tender for transmission infrastructure connecting its three planned plants to the grid.
The contract covers construction of the Miljevina substation and lines linking the B1, B2a and B3 plants to the network serving Foca and Sarajevo. Bids are due by 14 December.
The EPC+F tender requires the contractor to arrange financing as well as engineering, procurement, construction and commissioning. Works must be completed within two years after building permits are secured.
The project’s estimated cost has risen from about €103 million to more than €171 million, partly due to additional works and landslide-related measures.
The three cascading plants are being developed with China’s AVIC. Construction began in December 2021.