The investment cost of Bosnia and Herzegovina’s Bistrica hydropower project has increased by approximately two-thirds, raising concerns over construction risk, capital requirements and the financial exposure of state-controlled electricity companies.
The project’s estimated value has risen from an original €102.5 million to more than €171 million, representing an increase of roughly 66%.
The latest development follows approval of an additional €11 million recapitalization of project company HE Bistrica by shareholders representing state capital.
The transaction is intended to convert previously extended loans into equity, supporting the continuation of construction under a contract with Chinese engineering contractor AVIC.
It follows a separate €7 million capital increase approved at the end of February 2026, adding to earlier financial support since construction began in late 2021.
The escalating investment cost has become the central issue surrounding the project.
Additional construction requirements and works associated with landslide remediation have contributed to the increase. However, shareholder records indicate that the complete explanation for the higher project cost has not yet been clearly established.
The uncertainty is particularly important because additional financing is being committed while the final investment requirement remains open to question.
The Investment and Development Bank, representing state capital, also raised concerns about the planning basis used to authorize the latest recapitalization.
The additional expenditure was expected to be reflected in Hidroelektrane na Drini’s 2026 business plan, although the plan had not yet been formally adopted or reviewed when the shareholders made their decision.
The project’s ownership history adds another dimension to the financing debate.
The state sold HE Bistrica to Kaldera Company for €3.5 million in 2008, before reacquiring the company in 2019 for more than €11 million.
The subsequent increase in construction costs has placed renewed attention on the cumulative financial commitments associated with the development.
For electricity sector investors and lenders, the case illustrates the difficulty of controlling capital expenditure on hydropower projects affected by geological conditions, changing construction requirements and extended implementation schedules.
Cost escalation can materially alter project economics. Higher investment requirements increase the amount of capital that must eventually be recovered through electricity sales, while delays postpone the start of operating cash flow.
The project also demonstrates why financial oversight must extend beyond the original construction contract.
Updated cost estimates, documented variations, geological risk assessments and clearly approved financing plans become increasingly important when a project’s budget rises substantially.
Bistrica remains under construction, but the latest recapitalization does not by itself establish a final investment cost. That distinction will remain central to assessments of its financial viability.