Bosnia and Herzegovina’s Republic of Srpska has launched a concession procedure for the proposed 168 MW Tolanovo wind farm, opening a new renewable energy investment opportunity near Nevesinje with an estimated project value of €102 million.
Local developer Adria Energy Wind is seeking to develop the facility on the Tolanovo mountain ridge, approximately 25 kilometres south of Nevesinje, at elevations ranging from 930 to 1,150 metres.
The project is expected to generate approximately 451.4 GWh annually, with its entire production intended for sale on the electricity market rather than being reserved for a specific industrial consumer.
The Republic of Srpska Ministry of Energy and Mining has opened the public concession procedure, with the operating concession potentially extending for up to 50 years.
The project’s advancement comes as southeastern European electricity markets attract additional wind investment, although network connection requirements, permitting and exposure to wholesale prices remain significant factors in financing decisions.
Under the concession terms, the successful investor will be responsible for securing access to the electricity transmission network and developing the infrastructure required to connect Tolanovo to the existing grid.
These obligations extend beyond turbine installation. The concessionaire will also need to resolve land ownership and legal matters covering the project site, access infrastructure and the transmission route.
Applicants must submit a feasibility study addressing technical and economic viability alongside environmental protection requirements.
The projected annual production indicates a substantial contribution to regional renewable electricity availability. However, the project’s commercial performance will depend on the cost of its grid connection, construction financing, operating conditions and the prices achieved for electricity delivered to the market.
For potential lenders and equity investors, the concession provides an initial development framework rather than confirmation that the project is ready for construction.
The central investment question is whether the proposed generation revenues can support both the wind farm itself and the transmission infrastructure needed to deliver its electricity to regional buyers.