Completion of four month major overhaul project on Unit B2 of Power Plant Nikola Tesla (TENT) B in Obrenovac is about to be completed and its connection to the grid is expected on 10 september.
B2 overhaul is the biggest modernization project on TENT this year and is going within the plans and major work which influenced the time duration of the project is modernization and reconstruction of the electrostatic precipitator
This very complex project is financed mostly from EU donations, works realization is managed by polish Rafako who won on tender earlier and local partners are companies from Serbia, Gosa and Izoprogres.