Croatian electricity market operator HROTE announced that at the beginning of September 2016 total installed capacity in wind farms in Croatia reached 417.95 MW.
Croatian company Viadukt announced that it has concluded the contract for execution of a portion of construction works for Krs Padjene wind farm in Sibenik-Knin County.
The investor is local company Lager Basic and the value of the contract amounts to 11.12 million euros without VAT. The deadline for the construction of 110 MW wind farm Krs Padjene is 14 months.
Croatian electricity market operator HROTE announced that at the beginning of September 2016 total installed capacity in wind farms in Croatia reached 417.95 MW. Some of the largest wind farms in Croatia are: wind farm Danilo (43.7 MW), wind farm Vratarusa (42 MW), wind farm Kamensko-Vostane (40 MW), wind farm Jelinak (30 MW), wind farm Ponikve (37 MW), wind farm Bruska (37 MW) and others.