DPM Metals is moving its Čoka Rakita gold project in eastern Serbia toward construction in early 2027, using equipment from its closed Ada Tepe mine and cash flow from existing Balkan operations to lower the development burden of its next regional mine.
The company confirmed that equipment from Ada Tepe in Bulgaria is being dismantled and refurbished for transfer to Čoka Rakita.
Reusing existing equipment could reduce procurement requirements, shorten delivery schedules and lower part of the capital expenditure compared with purchasing an entirely new processing and infrastructure package.
Construction remains targeted to begin in early 2027.
That makes Čoka Rakita increasingly central to DPM’s growth strategy as the company seeks to add another producing asset to its Balkan portfolio.
The Serbian project also benefits from DPM’s existing operating platform in Southeast Europe, including technical teams, procurement experience and mining infrastructure developed through its Bulgarian and Bosnian operations.
DPM produced approximately 97,000 gold-equivalent ounces across its operations in the third quarter, leaving it positioned toward the upper end of its 2026 production guidance.
That operating performance is important for Serbia because stronger cash generation gives the company greater ability to finance project development internally.
The Vareš mine in Bosnia and Herzegovina contributed around 45,000 gold-equivalent ounces during the quarter, while Chelopech in Bulgaria produced approximately 50,000 ounces.
Vareš is also ramping toward annual processing capacity of around 850,000 tonnes by the end of 2026.
For Čoka Rakita, however, the more important issue is how quickly DPM can convert the Serbian discovery into a construction-ready mine while maintaining capital discipline.
Reusing Ada Tepe equipment provides one obvious source of savings.
The company can potentially avoid part of the cost and lead time associated with new plant procurement while relying on machinery that has already operated within its own production system.
That also reduces commissioning uncertainty compared with introducing an entirely new equipment configuration.
The strategy reflects DPM’s broader approach to Balkan development: use established regional operations to support new projects rather than develop each asset as an isolated greenfield investment.
For Serbia, Čoka Rakita could become one of the country’s more important new precious-metals developments if the project remains on schedule.
The immediate milestones are completion of detailed development work, preparation of transferred equipment and maintaining the timetable for early-2027 construction.
The investment case is therefore shifting from discovery toward execution.
DPM already has operating mines generating cash elsewhere in the region. The key question for 2027 is whether that operating platform and the reuse of Ada Tepe equipment can translate into a faster and more capital-efficient build at Čoka Rakita.