EPCG and Japan’s PowerX signed a memorandum of understanding setting an indicative target of about 500 MWh of battery energy storage system capacity in Montenegro over an initial three-year period. The opportunity is to coordinate storage with EPCG’s flexible hydro resources, expanding solar output and regional electricity trading, rather than assess batteries as standalone arbitrage assets. The target is material for Montenegro’s relatively small power system.
For Montenegro, the 2026 energy balance envisaged roughly 198 GWh of solar generation, while planning expected solar capacity to reach around 215 MW as prosumer and utility projects expand. Adding weather-dependent solar to a portfolio with hydro inflows creates a need to manage changes in output and balance. Battery storage could help EPCG reduce imbalances across that portfolio.
Reservoir hydro can shift large volumes of energy over longer periods, but is subject to hydrological and water-management constraints. Batteries can respond within seconds, absorb short solar surpluses and support intraday trading without changing water releases. Coordinating the technologies could preserve reservoir value for periods when hydro’s longer-duration flexibility is more valuable, while using batteries for shorter-term changes in supply and demand.
Across the region, Montenegro’s power system is connected to Serbia, Bosnia and Herzegovina, Albania and the Italy link. A battery could charge when Montenegro has surplus power or imported electricity is cheap, then discharge into domestic demand or regional scarcity. This gives storage a potential role in managing imports and exports as well as local generation, within a power system linked to neighbouring markets.
The commercial model should optimise EPCG’s whole portfolio, not treat the battery energy storage system as an isolated profit centre. Its value should be measured by its incremental contribution to hydro, solar, imports, exports and the company’s balancing position. System-level benefits from coordinating storage with those activities can support a stronger investment case than relying on day-ahead arbitrage alone. The memorandum sets an indicative target; the facts do not specify a final investment decision or project schedule beyond the initial three-year period.