European electricity distribution investment is expected to reach €48 billion in 2027, as expanding renewable generation, battery storage and electricity demand put pressure on networks.
Annual spending across the EU and Norway rose from €24 billion in 2021 to €36 billion in 2024. Further investment will be needed to connect new projects and reinforce infrastructure built for a less decentralised electricity system.
Connection applications illustrate the scale of the challenge. Italy has about 348 GW of variable renewable capacity seeking network access, alongside approximately 277 GW of storage applications at transmission level. Germany’s storage queue is roughly 480 GW.
Those figures exceed the capacity likely to be built, with applications including speculative or overlapping projects. They nevertheless expose a growing mismatch between development pipelines and available network access.
Operational utility-scale storage across the EU more than doubled during 2025, reaching about 11.2 GW by early 2026. Germany accounted for approximately 2.9 GW.
Funding alone will not resolve connection delays. Permitting, equipment availability, labour shortages and the speed at which regulated operators recover investment costs remain constraints.
For developers, the commercial value of a renewable or storage project increasingly depends on securing a credible connection timetable alongside land, permits and financing.