Greek electricity transmission system operator ADMIE informed that after performing security calculations at the SEE region and taking into account the modification of annual maintenance program in GR-BG interconnection for 2020, the NTC is increased to 550 MW (GR<>BG in both directions) for the period between 24 and 30 April 2020. These quantities will be allocated on daily auctions in accordance with relevant JAO Auction Rules.