Greece plans to impose an annual €15,000 per MW levy on new data centres while requiring developers to secure renewable electricity from new domestic generation facilities, introducing a financing framework that could significantly increase the cost and complexity of artificial intelligence infrastructure investments.
The measures, included in electricity-market legislation submitted to parliament on October 31, would require data-centre operators to finance their grid connections, provide financial guarantees of €200,000 per MW and ensure at least 60% of annual electricity consumption is covered by qualifying new renewable generation.
For a 100 MW data centre, the proposed annual levy would amount to €1.5 million, alongside a €20 million grid-connection guarantee and the cost of associated electrical infrastructure.
The guarantee is financial security rather than an upfront non-refundable fee, but securing it could tie up liquidity or banking capacity during development.
The legislation remains subject to parliamentary approval.
The revised framework represents a significant shift in Greece’s approach to electricity-intensive digital infrastructure, moving from conventional grid-access approvals towards a model in which developers assume greater responsibility for new electricity capacity, network costs and benefits to local communities.
For infrastructure investors, the commercial implication is that data-centre financing will increasingly depend on the integration of computing infrastructure, dedicated electricity supply and long-term network-access rights.
Annual electricity-capacity levy introduces recurring infrastructure costs
The proposed €15,000/MW annual levy would be calculated against a data centre’s maximum electricity-consumption capacity and become payable when the facility begins operating.
Revenue would benefit residential electricity consumers and municipalities in areas hosting the installations, providing a mechanism for sharing part of the financial benefits of large digital infrastructure investments with local communities.
The levy introduces a recurring operating cost determined by contracted or installed consumption capacity rather than actual annual electricity use.
A 100 MW installation would face €1.5 million annually, equivalent to €15 million over ten years, before any subsequent changes in the regulatory framework.
For a 300 MW installation, the annual obligation would reach €4.5 million.
These amounts are separate from electricity procurement, network tariffs, maintenance, cooling infrastructure and other operating expenditure.
The levy could influence data-centre site selection, investment returns and infrastructure leasing arrangements, particularly for developments whose electricity capacity is reserved ahead of full commercial utilisation.
The proposed measure excludes data centres already operating and connected to the electricity network.
For new projects, however, the recurring charge would become an additional component of long-term financial modelling.
Renewable electricity must come from additional generation
A second change concerns the requirement that at least 60% of annual electricity consumption be supplied by renewable energy.
The revised legislation specifies that qualifying electricity must come from new renewable generation installations connected to Greece’s interconnected electricity system.
The requirement is intended to prevent large data-centre developments from satisfying their electricity obligations solely through existing renewable generation.
Eligible renewable installations must meet defined development conditions and be operational no later than the date the data centre is energised.
Where the required renewable generation or associated storage infrastructure is not operational, the data centre’s energisation could be suspended until those obligations are satisfied.
The legislation also restricts operating subsidies for the portion of qualifying generation and storage capacity used to meet the data-centre requirements.
The 60% obligation is calculated annually, rather than through mandatory hourly matching of generation and consumption.
This distinction allows greater flexibility in electricity procurement but still creates substantial development and contractual obligations.
The proposed framework would permit the renewable share to be adjusted through a ministerial decision under specified conditions, including arrangements involving non-solar renewable technologies or generation combined with storage.
For investors, renewable procurement would therefore become an integral part of the initial development structure rather than an arrangement that can be finalised after the data centre is built.
Grid connection becomes a major financial commitment
The legislation retains a requirement for developers to provide a financial guarantee of €200,000 per MW when applying for electricity-grid connection capacity.
The mechanism is designed to discourage speculative applications that reserve scarce network capacity without sufficient evidence of financial or technical maturity.
A developer seeking a 200 MW connection would need to secure a €40 million guarantee, while a 300 MW project would require €60 million.
The guarantee requirements are accompanied by stricter documentation covering project maturity, financial capacity, land rights and permitting.
Developers would also assume the full cost of connection works and network reinforcements required exclusively by their facilities.
This creates a financing structure involving several distinct obligations: the data-centre construction investment, electricity-network connection costs, credit support for capacity applications and long-term electricity procurement.
For lenders, these obligations must be assessed alongside the creditworthiness of the intended computing customers and the commercial timetable for filling the facility.
A data-centre project may secure land and technology partners but still face substantial development risk if the required electricity infrastructure cannot be completed on schedule.
Similarly, a delay in delivering the renewable generation needed to satisfy the new rules could postpone the entire investment’s operating revenues.
Large projects face additional infrastructure requirements
The draft legislation also establishes special treatment for electricity-connection applications exceeding 200 MW.
Such projects could receive priority assessment where they are accompanied by qualifying new dispatchable generation or electricity-storage infrastructure capable of meeting specified technical and capacity requirements.
The framework links this treatment to additional infrastructure corresponding to at least 80% of the proposed data centre’s maximum electricity-consumption capacity, subject to the detailed eligibility rules.
The measure reflects the growing challenge posed by large, continuous electricity loads that can place significant demands on transmission infrastructure.
For major international investors, the implication is that obtaining priority network access may require investment in substantial energy infrastructure alongside the digital facility.
This could favour developers with experience financing and coordinating complex electricity and industrial projects.
It may also strengthen opportunities for partnerships between data-centre operators, electricity utilities and infrastructure funds.
However, preferential assessment does not itself guarantee the availability of grid capacity or completion of the required investments.
Banks face a new combined infrastructure-financing model
The revised framework could change the way banks evaluate data-centre investments.
Traditionally, data-centre financing has focused on construction expenditure, equipment, customer contracts, operational reliability and long-term infrastructure revenues.
Under the proposed Greek model, lenders must also assess renewable generation schedules, grid-connection guarantees, network reinforcement costs and the risk of delayed energisation.
The coordination between electricity and computing infrastructure becomes especially important.
A delay affecting an associated renewable project could prevent the data centre from commencing commercial operations, even where the physical building and computing equipment are complete.
For lenders, this creates a need for integrated technical due diligence, including electricity-load studies, connection agreements, renewable procurement arrangements and construction-interface risks.
Financing agreements may also need clearer provisions addressing delays, completion tests, contingent liabilities and responsibility for compliance with electricity-supply obligations.
The regulatory framework could consequently favour developers capable of securing coordinated financing for both digital and electricity infrastructure.
Southeast Europe faces a new competition for AI infrastructure
Greece’s proposed model has wider implications for Romania, Serbia, Bulgaria, Croatia and Montenegro, where data-centre and digital-infrastructure investment could become increasingly important to electricity-demand growth.
These countries have different electricity systems, regulatory frameworks and levels of infrastructure readiness.
Nevertheless, investors comparing locations will increasingly need to examine more than electricity prices or land availability.
Grid-connection certainty, access to reliable power, telecommunications infrastructure, regulatory conditions and the financial cost of securing electricity capacity could become decisive factors.
For Serbia, the development provides a reference for evaluating large industrial and digital infrastructure investments in a market where grid-access availability and the timing of network development are important investment constraints.
Romania and Bulgaria could also compete for regional data-centre investment, benefiting from EU market access and established industrial infrastructure.
Montenegro’s potential will depend on the scale and location of suitable projects and the ability to support additional electricity demand without disproportionate network investment.
The Greek requirements do not apply in these neighbouring markets, but they illustrate how governments may increasingly seek to ensure that new electricity-intensive investments bear a greater proportion of the infrastructure costs they create.
Electricity availability becomes an investment asset
Greece’s proposed legislation signals a changing relationship between the energy sector and the digital economy.
For data-centre developers, access to reliable electricity is becoming a strategic infrastructure asset requiring dedicated financing, regulatory approvals and long-term contractual commitments.
For electricity companies, the commercial opportunity extends beyond supplying megawatt-hours.
Utilities and infrastructure developers could participate in preparing grid-ready sites, developing qualifying electricity supply, constructing electrical infrastructure and structuring integrated investments with international technology companies.
For banks and infrastructure funds, the most valuable projects may be those capable of demonstrating secure electricity access, coordinated generation development and credible long-term computing demand.
The proposed annual levy and stricter renewable requirements increase upfront complexity and recurring costs, but they may also help distinguish financially credible investments from speculative applications for scarce grid capacity.
The legislation’s final provisions and implementation rules will determine the full financial consequences.
The broader market shift is already visible: AI infrastructure investment is becoming inseparable from electricity infrastructure finance, with grid capacity, energy supply and regulatory obligations increasingly determining which projects are commercially bankable.
For Southeast Europe, competition to attract data centres may therefore depend less on offering the lowest electricity price and more on providing dependable, financeable electricity infrastructure within the timetable required by international technology investors.