Data centre connection requests submitted to Greek transmission operator ADMIE have reached approximately 9 GW, intensifying competition for high-voltage capacity and raising questions over how projects should be prioritised.
Applications have increased from just under 5 GW in mid-June. The total represents requested connections rather than confirmed construction or future electricity consumption.
Authorities are examining whether the existing first-come, first-served approach should give way to a system prioritising more advanced developments.
The concern is that projects without sufficient permits, financing or commercial backing could reserve scarce capacity for years, delaying investments that are ready to proceed.
Grid constraints are also influencing location choices. Congestion in Attica is encouraging developers to consider sites beyond the Athens area.
A PwC roadmap estimated potential capacity of approximately 630 MW in western Macedonia, 605 MW in Thessaly, 485 MW in central Macedonia and 480 MW in central Greece. These estimates should not be treated as guaranteed connection offers.
Developers must also assess access to reliable electricity, cooling requirements and the cost of network reinforcement.
The growing application queue demonstrates investor interest, but the decisive commercial advantage will belong to projects that secure a deliverable connection rather than merely a place in the queue.