Greenvolt Group has secured €284 million in project financing for its 253.1 MW Gurbanesti wind farm in Romania, bringing financing arranged for its two-project Wind Rose platform to €632 million.
Gurbanesti is under construction in Călărași county and is scheduled to enter commercial operation by the end of 2027.
The project will use 42 GE Vernova turbines with 158-metre rotor diameters, under a supply agreement announced in December 2025. It spans the municipalities of Gurbanesti, Nicolae Bălcescu and Valea Argovei.
Support secured under Romania’s Contracts for Difference scheme, including through the August 2025 auction, provides a more predictable revenue base for part of its future production.
Eight institutions are participating in the financing: UniCredit, Erste Group Bank, Banca Comercială Română, Siemens Bank, Société Générale, BRD, ING Bank and Alpha Bank.
The second Wind Rose development, the 253.1 MW Ialomița wind farm, is also under construction and expected to begin operating in 2027. Greenvolt arranged €348 million of financing for that project in February.
The KKR-backed group reports a Romanian development portfolio of 707 MW of wind, 58 MW of solar and 209 MW of battery storage.
With financing secured for roughly 506 MW across the two wind farms, the platform’s next milestone is delivery: construction, grid connection and commissioning must now convert the funding commitments into operating assets.