Montenegro: TPP Pljevlja’s 2020 production plan was exceeded
, SEE Energy NewsCoal-fired thermal power plant Pljevlja has exceeded electricity production plan for 2020 by 12.9 %, sad Montenegrin state-owned power utility EPCG. The statement from the company said that TPP Pljevlja produced a total of 1.487 TWh of electricity in 2020. It also said that, out of the planned 2.987 TWh of electricity to be produced by all facilities operated by EPCG in 2020, 2.817 TWh were produced or 94.3 % of the planned amount.