Romania’s Nuclearelectrica will seek shareholder approval for €800 million in European Investment Bank financing to refurbish Cernavoda unit 1, advancing funding for an overhaul intended to extend the reactor’s operating life to 2060.
Shareholders are due to consider the proposal at an extraordinary general meeting scheduled for October 29–30.
The financing is expected to comprise two €400 million loans, with the first targeted for signing in 2026 and the second in early 2027. The EIB approved the financing in July.
The 700 MW reactor is scheduled to undergo its main refurbishment during 2027–2030, including reactor retubing and other major works. Testing and commissioning would precede its planned return to service in 2030.
Civil works began in 2025 and continued through 2026 alongside engineering, licensing, procurement and financing preparations.
Nuclearelectrica plans to combine internal resources with funding from international financial institutions, export credit agencies and commercial banks. It previously secured a €540 million syndicated loan in September 2025 for the preliminary stage, with JP Morgan SE leading the lender group.
After refurbishment, unit 1 is expected to supply about 9% of Romanian electricity between 2030 and 2060.
Securing the loans would strengthen the funding structure, while the scheduled outage leaves Romania needing replacement supply during the overhaul.