Region, Curtailment on IT-ME border between 10 and 11 December
, SEE Energy NewsSEE CAO announced that, based on instructions from TERNA and CGES, SEECAO announced that NTC on IT-ME border will be curtailed between 10 and 11 December 2022 in order to ensure operation remains within Operational Security Limits.
The curtailment will start on 10 December at 08:00 (CET) and will last until 11 December at 20:00 (CET). During this period, NTC in both directions will be reduced to 210 MW instead of 600 MW.