Power plant Ugljevik which a part of power utility ERS of Republika Srpska was a realiable electricity generation facility in 2015.
Power plant Ugljevik achieved production of 176 Gwh in august which was the increase compared with planed monthly level of 148GWh.
Since January 2015 TPP Ugljevik produced 1.105,65 Gwh compared with planed 1.043, this result shows the accomplishment of 105%.
Better results than planed were achieved due to the quality maintenance and management of the units of power gen facility but also due to the successfully completed regular annual overhaul explained Dragan Miljanovic director for technical affairs in TPP Ugljevik. , transmits Serbia-energy.eu