Romanian nuclear producer Nuclearelectrica has cut its forecast 2026 net profit by 42.9% to €221 million, as prolonged outages at Cernavoda reduce electricity sales and force the company to purchase replacement power.
The revised financial plan assumes both reactors will return to the network on November 1. That date is a planning assumption underpinning the company’s projections.
Expected electricity generation has been reduced to 6,743 GWh, from 9,080 GWh, a decline of 2,337 GWh, or approximately 25.7%, against the original plan.
The production shortfall is affecting both sides of the company’s accounts. Forecast total revenue has been lowered 14.9% to €943 million, including a reduction of approximately €188 million in expected electricity-sales revenue.
Projected expenditure has increased 3.6% to €676 million, partly because the company has needed to buy electricity to replace unavailable nuclear production.
Exceptionally low Danube water levels disrupted cooling-water availability at the plant. Unit 1 was taken offline on July 28, followed by Unit 2 on August 13.
Both reactors have remained unavailable while authorities implement measures intended to improve water supply conditions. In September, Romania’s emergency authorities adopted a phased response plan addressing the prolonged decline in Danube levels.
Cernavoda normally generates around 20% of Romania’s electricity, making the loss of both units significant for the national supply balance.
Each reactor has a capacity of approximately 700 MW. Unit 1 entered operation in 1996, followed by Unit 2 in 2007.
Romania is also pursuing a longer-term expansion of the complex. Planned Units 3 and 4 would add a combined 1,400 MW, with commissioning currently targeted for 2030 and 2031.
The immediate financial outlook, however, depends on restoring the existing reactors. Any extension of the outages beyond the assumed November restart would leave the company exposed to further lost production and replacement-electricity purchases.