Power plant Nikola Tesla B plant plans a capital overhaul of B2 unit to start on 1may 2016.
New rotor 70t wight was delivered last week in Power plant Nikola Tesla B TENT B and will be installed on the B2 unit during its capital overhaul project. This is the part of planed procurement of new generator of power 727,5MW.
Capital overhaul on B2 unit is pland to start on 1.may stated Goran Lukic TENT B director. Stator of generator is currently on factory inspection and will be delivered on the day of rotor erection during the upcoming overhaul of 180 days.
The value of new generator is 3.2MEUR, produced by Alstom Power GE Power, transmits Serbia-energy.eu