The largest production capacity in the “Serbia Power Utility Company”, the Power plant “Nikola Tesla A” enters successfully in the finals of this year’s race for the production result , and even two of its six units have completed the annual production task even before the end of November.
Unit A 2 produced and delivered 904 million kilowatt hours of electricity to the system on 8th November, which was exactly the amount planned for the whole 2013th. This unit completed annual production plan even 52 days earlier.
Unit A 4 achieved an excellent result which realized its annual production task on 27th November, delivering to the system more than 1.7 billion kilowatt hours of electricity.
Source; Serbia Energy.EPS