The conditions for the project realization of HPP “Zvornik” revitalization and modernization were fulfilled after a long time period. Meeting with all contractors, equipment suppliers, consultants and professional team, at which the basic operation principles of the project implementation were agreed, was held yesterday in HPP “Zvornik”.
The meeting was attended by representatives of the general contractor ” Voith Hydro ” , subcontractors – Institute ” Mihajlo Pupin ” , “Gosa Montaza” and ” Elnos ” , consultants , representatives of the ” Serbia Power Utility Company” and company “Drinsko – Limske HPPs” . At the meeting, the investor required from equipment supplier to submit detailed schedule activities on the project, in compliance with the new terms of the Agreement entry into force. After several hours of the meeting, all participants visited HPP “Zvornik” , informed about the locations at the construction site , locations for equipment storage and office space.
Source; Serbia Energy