Developer Baranda Energetski Park is advancing a proposed 317 MW solar project near Opovo, with a 31.7 MW/126.8 MWh battery, but sensitive land conditions will shape its development timetable.
The project would occupy approximately 401.55 hectares, much of it former fishpond land. Estimated annual electricity generation is around 500 GWh.
Parts of the site fall within the Srednje Potamišje Important Bird Area and Serbia’s ecological network. A protected habitat near Baranda must remain free of construction.
Vegetation beneath the panels would need to be managed through mowing or grazing rather than chemical pesticides.
The battery’s proposed configuration provides approximately four hours of discharge at rated power, allowing some daytime generation to be shifted into later periods. Network connection is planned through a new 400/35 kV substation.
The developer has requested a decision on the scope of the environmental impact assessment from the provincial authorities.
Archaeological conditions add another scheduling requirement. A systematic field survey is required at least 12 months before construction, followed by archaeological supervision during excavation.
The proposal combines substantial solar generation with storage, but environmental clearance, archaeological work and a deliverable grid connection will determine when it can become an investable construction project.