In May 2026, the Krško Nuclear Power Plant, jointly operated by Slovenia and Croatia, generated a total of 517,109 MWh of net electricity, slightly exceeding the planned output of 515,000 MWh by 0.41%.
For comparison, in May of the previous year, the plant produced 519,322 MWh of net electricity, which was also above target, surpassing the planned level of 515,000 MWh by 1.89%. This shows consistently stable performance close to the scheduled generation plan.
The plant operated under normal conditions in line with its technical specifications, with all safety systems fully functional throughout the month. Both the availability factor and capacity factor reached 100%, indicating uninterrupted operation and full utilization of installed capacity.
No technical issues or operational disruptions were reported during the period, confirming continued reliable performance of the facility within the regional power system.