Slovenia could begin construction of the long-delayed Mokrice hydropower plant in late 2027 or early 2028, although the project still faces permitting and potential legal hurdles.
The plant would complete the chain of hydropower facilities on the lower Sava River and provide both electricity generation and flood-protection functions.
A key government decision is approaching after Environment and Spatial Planning Minister Polona Rifelj signed documentation required for consideration by the government.
If approval proceeds, the ministry plans to continue the remaining administrative process with the aim of issuing a construction permit during the first half of 2027.
That timetable is not yet assured.
The Slovenian Society for the Study of Fish could lodge another appeal, potentially returning the project to the Administrative Court. The court has already considered the case twice.
GEN Energija chief executive Andrej Vizjak has said further legal proceedings remain possible, but maintained that the principal environmental and technical concerns have been addressed in the project design.
The remaining uncertainty is therefore increasingly linked to the legal status of administrative decisions rather than fundamental engineering questions.
The project has been developed as a multipurpose facility, combining power production with flood protection and environmental measures intended to address nature-conservation requirements and the interests of surrounding communities.
The possibility of another court challenge means the proposed 2027-28 construction start remains conditional.
But after years of delays, progress on government approvals and permitting could move Mokrice closer to the investment stage.
For Slovenia, completion of the lower Sava cascade would add dispatchable renewable generation at a time when flexibility and system reliability are becoming increasingly important alongside the growth of variable renewable energy.