Serbia’s case should be read carefully. EMS has not technically “stopped all RES grid connections until 2030”; the practical effect is close to that for many new…
Browsing: EMS
Serbia’s latest move to delay new grid-connection studies for large variable renewable-energy projects is not just a technical intervention by Elektromreža Srbije. It is a market correction…
Serbia’s electricity market is entering a phase where access to the grid itself is becoming one of the country’s most valuable energy assets. For most of…
A major step in strengthening Serbia’s electricity transmission network has been taken as the transmission system operator EMS signed a contract for the upgrade of key…
Serbia’s transmission system operator Elektromreža Srbije is moving deeper into a structural overhaul of its high-voltage network, signing a key contract to upgrade the Bajina Bašta substation from 220…
In Serbia, viable renewable siting begins with transmission reality, not resource theory. EMS operates a compact, highly loaded system whose flexibility margin is constrained by cross-border flows,…
Elektromreža Srbije (EMS) has in recent years constantly stood at the center of energy debates, strategic announcements and major promises about modernization, European integration, support for…
Serbia is entering an energy decade unlike any it has experienced since the post-Yugoslav restructuring of its power sector. But while most public attention focuses on…
Serbia’s electricity transmission operator EMS has signed a contract with a consortium of construction firms to build the new 400/110 kV Belgrade 50 substation in Ugrinovci.…
Serbian electricity transmission operator EMS has commissioned the Institute of Architecture and Urban Planning of Serbia to prepare the spatial plan for the Central-Balkan Corridor, a…