Montenegro’s state-owned power utility EPCG is bracing for a significant financial shortfall in 2025, according to CEO Ivan Bulatović. To ensure a stable electricity supply for…
Browsing: tpp pljevlja
Montenegro’s key electricity producer, the Pljevlja thermal power plant, has been shut down for reconstruction and will remain offline until mid-November. The plant typically supplies over…
Montenegrin state-owned power utility EPCG has confirmed that electricity prices will remain unchanged for the time being. As the ecological reconstruction of thermal power plant Pljevlja…
Pljevlja Coalmine is set to lose 48 million euros in revenue this year due to the ongoing eight-month reconstruction of the Pljevlja Thermal Power Plant (TPP),…
As the Pljevlja Thermal Power Plant gears up for renovations next year, Elektroprivreda Crne Gore (EPCG) anticipates a shortfall of approximately 400 gigawatt hours (GWh) of electricity, amounting to an…
The power utility company Elektroprivreda (EPCG) has achieved significant exports in the first two months of this year, resulting in a profit of over 20 million…
Energy from renewable sources from sustainable locations in the Nikšić Municipality alone could supply more than 200,000 Montenegrin households, as announced during the presentation of the…
The Pljevlja thermal power plant will be shut down for several months in 2025 due to ecological reconstruction, which will force Montenegro to import large…
Pljevlja coalmine produced 1.86 million tons of coal in 2023, which is 8.1% higher compared to the previous year. The colamine supplied the thermal power plant…
According to announcements, due to reconstruction in 2025, Pljevlja Thermal Power Plant (TPP) will not work for six to seven months, which is why the energy…