In December 2012, The Company “Thermal Power Plants Nikola Tesla” produced and delivered to the electric power system of Serbia 2,039,863,000 kWh of electricity, that is 1.33% more than planned. Together with non-produced electricity because of the hot and cold reserve that amounts to 34,876,000 kWh, the production plan would be achieved with 103.07%. During this month a total of 13 downtimes were recorded, out of which 10 occurred in TPP NT, two in TPP “Kolubara” and one in TPP “Morava”.
TPP A produced and delivered to electric power system 1,029,421,000 kWh of electricity or 1.21% less than planned. Together with non-produced electricity (16,253,000 kWh) due to the heating reserve, the plan would be accomplished with 105.35%. Power Units А-1, А-3 and А-6 overfulfilled the monthly plan. The first two Units recorded continuous grid operation in December.
In the same period, TPP B produced and delivered to the power system 833,340,000 kWh of the electricity or 5.35% more than planned. Non-produced electricity due to the heating reserve (4,273,000 kWh) would have a minimum impact on the plan increase – 0.60%. This Power Plant did not have any downtimes in December, and the Unit B-2 was operating all the time on the grid.
TPP “Kolubara” produced and delivered to electro energy system 122,970,000 kWh of electricity and achieved plan with 108.82%. Together with the non-produced electricity (7.958.000 kWh) due to heating and cold reserve, the plan would be achieved with 115.87%. Power Unit A-3 had continuous operation on the grid and overfulfilled the monthly production plan, which was also the case with Unit A-5.
TPP “Morava” produced and delivered to the electric power system 54,132,000 kWh of electricity and achieved the plan with 80.79%. Together with the non-produced electricity (5,942,000 kWh) due to hot and cold reserve, the plan would be realized with 89.66%.
Via railway transport it was delivered 2,783,815 tons of coal to TPP NT A, TPP NT B, and TPPK, which is just 0.36% less than planned. TPP M received both from the underground and open pit mines 58,109 tons of coal, that made 109, 64% of the plan.
Specific consumption of liquid fuels in the Company TPP NT is by 8.37% lower than the standard being 2.15 g/kWh.
The participation of the Company TPP NT in the PE EPS without TPP “Kosovo”, amounts to 58.87% or 79.23%.
In the period January-December of 2012, the Company TPP NT produced and delivered to EPS 19,151,993,000 kWh of electricity by which they achieved the plan with 98.49%. With the electricity being non-produced due to hot and cold reserve, plan would be accomplished with 100.74%.
Source Kwh/Serbia Energy