The National Energy Company (NEC) “Ukrenergo” in January-May 2015 reduced the amount of power transmitted through main and interstate networks by 2.9% (to 1.607 billion kilowatt-hours) compared with the same period in 2014 – up to 53.092 billion kW- h.
According to the press service of the NEC, the cost of services of electric power transmission for the period increased by 15.6% (to 196.909 million USD) – up to 1 billion 459.625 million UAH.
At the same time calculations GP “Energy” with “Ukrenergo” for services in January-May of services as of 1 June 2015 was 75.4%.
Financing of capital investments in the development of backbone networks in the five months of this year amounted to 1 billion UAH 1.463 million, which is 2 times (by UAH 497.064 million) more than in January-May 2014.
“Ukenergo” five months transferred to the state budget 126 114 000 UAH of taxes and fees. Contributions to social insurance funds to pay employees amounted to UAH 160.931 million.
As reported, “Ukrenergo” in 2014 has reduced the volume of electricity transmission through main and interstate network by 2% (to 2.653 billion kilowatt-hours) compared with 2013 year – up to 129.842 billion kWh. Cost of services of electric power transmission in the past year decreased by 7.3% (to 242.099 million USD) – up to 3 billion 79,515,000 UAH.
“Ukrenergo” operates backbone and interstate power lines, as well as centralized dispatching the united energy system of the country. NEC is a state-owned enterprise, is under the Ministry of Energy and Mines. , transmits Serbia-energy.eu