TTP „Ugljevik“ 600MW and Hydro Power Plant “Mrsovo” constructions are announced to start in 2013. Investments are worth 1 billion euros. Company “Comsar Energy” got concession for it.“Comsar Energy” has already invested 13 million euros for preparatory work and coal reserves testing.
The preparatory work is for 700 million euros worth TTP with two independent 330 mw blocks which are being finished and the start of construction is expected to be in May 2013. Location conditions are obtained. Ecological licence is expected at the moment, and then building licence.
Company Director Sinisa Majstorovic said to newspapers that he will sign the contract with Chinese partners who work on plant project until 15.01, and the documentation will be finished by April.
800 workers will get job in the thermal power plant.
Source Serbia Energy Magazine