Region, Planned power plant maintenances relevant for week 8

, SEE Energy News

Planned power plant maintenances relevant for week 8:

– NPP Paks G5;G6 (Hungary) – 500 MW (02.02.2022 – 03.03.2022)
– Gas-fired TPP Lavrio G4 (Greece) – 250 MW (05.02.2022 – 16.03.2022)
– Gas-fired TPP Malzenice (Slovenia) – 420 MW (24.02.2022 – 18.04.2022)

Unplanned power plant outages relevant for week 8:

– Coal-fired TPP Nikola Tesla A4 (Serbia) – 329 MW (16.02.2022 – 01.03.2022)
– Coal-fired TPP Tuzla G4 (BiH) – 200 MW (05.02.2022 – )

– Coal-fired TPP Kakanj G5 (BiH) – 100 MW (25.01.2022 – )