“Electric Power Industry of Republika Srpska” (ERS) currently makes preparations for the plants overhauls and overhauls of thermal power plants and regular overhauls of HPPs systems on the Trebisnjica and HPP on the Drina and greater operation on HPP on the Vrbas, where the reconstruction of oversight -management system of power plant will be done”, told Director of Department for Development in ERS, Ilija Tamindzija.
According to him, ERS produced 5,570 gigawatt-hours of electricity in the power plants of the company until Wednesday, which are only 800 gigawatts less than the annual plan.
“It is expected to meet the annual plan of 5668.78 GWh by the end of the year, with the overthrow of twenty gigawatts. The amount of 5,600 to 5,700 gigawatts is something realistically expected that we produce per year with this installed capacity, provided that in the case of over planned hydrology, as it was last year, the results greater than these can be achieved “, says Tamindzija.