Due to the balance sheet for the last day restriction nuclear power plants in Ukraine under produced 36.10 million kilowatt-hours of electricity.
“For the past day, February 22, stations produced 243.39 million kWh of electricity,” – said in the press service of Energoatom.
Dispatching schedules of generation for Zaporozhye NPP – 3400 MW, Rivne NPP – 2435 MW, South Ukraine NPP – 2485 MW KNPP – 1 850 MW.
Balance restrictions as of 6:00 February 23 2016 is 1430 MW. On the balance sheet constraints worked: ZNPP-6 – 76%, the Rivne NPP-3 – 68% SU NPP-1 – 81%, the KNPP-2 – 86%.
On February 23, out of 15 nuclear power plants units of Ukraine 13 are operating. At Zaporozhye NPP power unit 1, they have 67th day of planned capital repairs. In addition, the power unit of the Zaporizhzhya NPP number 2 is also in 9 th day of planned repairs.
Epravda UA